Date: 11-11-2024
Place: Rotterdam, Netherlands
Inspector: François Corthals
ELEMENTS |
SIRE 2.0 REF |
OBSERVATIONS |
Process |
3.2.6 |
The initial
engineering audit was conducted by the vessel manager, a former chief
engineer, on 29-30 May 2024. The PIQ stated 12-21 July 2024. This audit was
actually conducted by a former senior deck officer. |
Hardware |
5.8.1 |
No proper
fall prevention device (cage or equivalent stainless-steel wire with fall
preventing device/belt) was fitted on the elevated ladders of the forward
mast and the Xmas tree. |
Hardware |
8.3.2 |
One of both
fixed oxygen detectors monitoring the air in the nitrogen generator area
showed 22.2%. The PMS required a 3-monthly calibration checks. The last check
was completed on 21 September 2024.Rectified during the inspection. |
Human "Junior Engineer
Officer: Not as expected. |
|
"Junior
Engineer Officer: Not as expected. The OP had not detected the high reading
of one of both fixed oxygen analysers in the nitrogen generator area while
the remote oxygen
reading was located near the entrance of the engine control room." |
Human "Senior Engineer Officer: Not as
expected. |
|
"Senior
Engineer Officer: Not as expected. The OP had
not detected the high reading of one of both fixed oxygen analysers in the
nitrogen generator area while the remote oxygen reading was located near the
entrance of the engine control room." |