Inspection

Location: Quintero, Chile

Date: 10th Jul 2025

Inspector boarded the Vessel around 2 hrs before pilot at Anchorage. Opening meeting in Master’s Cabin. While shifting from anchorage to MBM, documentation part (around 2 hrs) was done by himself in the Master’s cabin alone. All files and docs were kept ready as per his requirement. He is very senior and doesn’t like discussion and argument at all. Requested min persons while rounds.

In Master’s Cabin approx. 3 hrs
DDR and SMS policy for reporting the third party
Report of last External and Internal audits

Deck -
Started from the bridge
LSA items on bridge
Emergency contact list, as per him National contact details was not correct. If available in the list, oil response center’s contact details to be used. 
EMG Gen was started on battery and secondary means. Demonstration of resetting of quick closing valve.
Lifeboat engine started on both set of batteries one by one.
Bosun store bilge alarm


Bridge-
 Company UKC policy in detail specially meaning of deepest draft and summer draft.
 Couple of safety depths were out side LDL on ECDIS / Explained that its because of taking allowance for tide at the time of transit.
 GMDSS log especially the designated officer for communication and tests / Verified with Muster list.
 Passage plan for secondary means of position fixing in open waters / Verified with sight log.
 Arrival and departure tests and checks as per NAV 11 & 10.
 Tested fire alarms and verified location of alarm on fire alarm panel on bridge.
 Tested all Navigation lights.
 Emergency steering procedure and frequency of drill.
 Difference between X and S Band radar and purpose. Also which radar to use for SART.
 Cyber security manual and its purpose.
 Basic details about inhibitor cargo.
 Security assessment for the past voyage.
 Checked GMDSS radios.
 Checked Master standing order and verified call master criterias.
 Method of ordering charts and publications (Auto or Manual) / Also checked NAVTRACKER software and NAVTOR NAVBOX for NAVSTICK.
 IALA Buoyage system – Current area, System of buoyage (Bound North to south or South to North)

CCR-
1- Inspector first checked Shop Shore Safety Checklist and then asked question about wind/swell criteria to stop/hose disconnection / un-berth the vessel.
2- Checked cargo plan and asked about stages and confirm vessel is following.
3- Asked about gas meter and dragger tube on board.
4- Asked about inhibited cargo.
5- OPS-02, Pre arrival checklist.
6- Asked about BWTS systems and working principal.

Obs-
7- HVPQ- Split drum was fitted but was selected as “No”
8- Emg Gen room- insulation gloves were tested as per EN 60903.
9- Undue risk to crew due to mooring pattern used
10- Warping drum painted
11- Chemical locker- chemical gloves in poor condition
12- Steering gear reserve tank level gauge plastic cover holed and cracked
Location: Castellon, Spain

Inspector is very calm, wait for your answers. But others should not interfere when questioning.

Bridge
DPA poster
ECDIS service History
NP133C entries for last ECDIS update
AIS Overview
ECDIS layers
ECDIS alert and alarm logs
ECDIS safety settings & Calculations
UKC pro forma for the voyage
Depth cross checked with load port and discharge port CD
PVM and interval in Gibraltar straits
BWL and EWL in Gibraltar straits
BNWAS
E/R Alarm during UMS. What are the actions you take as D/Off(Deadman Alarm procedure)
EPL system 
Passage Plan cross checked randomly with ECDIS markings
ECDIS UPS renewal and back up time
Management of Distractions on Bridge- Where it is in SMS
Pilot Card & MPX
GMDSS log checked, but no questions asked 

Questions were not that deep, asked only the questions coming up in tab. Completed the Inspection with 1 positive observation regarding UKC calculations. Thank you all for your support.

Inspection 

Place: Manzanillo, Mexico  

He boarded 0520 Lt in morning. Because we were remaining with only 2 hours cargo discharge completion. While boarding at gangway, Asked the Duty AB, what all cargo discharge goin on. After the opening meeting in conference room at Opening formalities  
 
Bridge 
  1. Asked regarding if ecdis has newly installed 
  2. What all checks and tests to be carried out prior long sail.
  3. Check thoroughly all ecdis, tools , sensors, enc's.  
  4. Weekly latest update.
  5. Checked for chart compilation scale.
  6. Checked thoroughly full Passage Plan on ECDIS as well as paper plan
  7. Checked if catzoz had been applied 
  8. Checked bwl /Erwl, security level
  9. Checked if chief engineer had crosschecked and signed it.
  10. Asked about safety setting 
  11. How do we apply or and it's uses and definition 
  12. Confirmed if there is any defect in bridge equipment's,  I informed whatever was there
  13. Asked about radars both condition
  14. Radar x and s band difference, magnetron running hours.
  15. Magnetron Replacement policy from radar manual.
  16. How will we check P.I and it's uses. And how to apply it. 
  17. Which radar we'll use in rain. 
  18. Which speed input we'll use for collision avoidance.
  19. How we'll check performance monitor and it's uses and need.
  20. Asked about company policy for use of AIS for collision avoidance 
  21. Checked Nav lights , tested function using taking out the fuse. Lamp test performed
  22. UKC policy while at berth ? and at berth, why it is 1.5 % of the ships breadth.
  23. Squat effects shallow and safety contours 
  24. GMDSS Battery Annual Test record, 
  25. Gmdss tests why it is been done 
  26. Lrit and ssas tests
  27. What is the purpose of gmdss and it's tests, Checked gmdss log book.
  28. Last monthly and Weekly tests.
  29. Mainly Asked 
  30. When and where will you not test gmdss Annual battery load test?
  31. Gmdss shore based maintenance certificate.
  32. Checked and Asked for ENC's updating and how are you maintaining enc and charts for updating.
  33. Weekly (asked AIO and what is AIO.)

Deck rounds 
  1. Asked pumpman about ESD
  2. Static accumulator, static cargo or not.
CCR
  1. Asked about general equipment's and checklists
  2. Mooring, msmp, line management as per company policy checklists.
  3. Accommodation inspection checklist.
  4. Safety officer checklist
  5. Cargo checklists plans , etc.
  6. asked Bosun some questions
Engine room rounds
  1. Asked check gauges fuel pump and others 
  2. Asked questions to 2nd engineer 3rd engineer.
  3. Them one tor ch eng cabin , Checked for records and plans and books 
  4. Asked various questions regarding fuel , Marpol.
Master cabin
  1. Checked various documents.
Vessel comment: Overall he was ok with us, Mostly when he asked questions and if we are not able to answer, He will guide and answer on his own.
Inspection 
Place: New York 


Bridge 
Ecdis latest enp 
Echo sounder principal 
Last gmdss weekly 
Sart and epirb function 
T and P for route
Immersion suit and lifejacket (to check jip and light )
Radar chracterstics
Range of aldis lamp 
(What will be there one situation where you actually see the radar for collision avoidance and as per which rule )

CCR

Maximum velocity of flame arrestor  
Span gas calibration 
IG requirement and composition 
Deck seal, pv breaker 
Setting of pv valve in vecs mode , inerted and non inerted
What is angle of loll 
How you correct 
Fixed detection system alarms 
What action will take if cargo leaking in balast tank ?

Normal round on deck 

4 observation but nothing major. 


Inspection 

Place: Santos.

Bridge
• Demonstrate how you will change GPS datum.
• ⁠What is GPS antenna offset and how you will change the value.
• ⁠Checked UKC calculation sheet in detail.
• ⁠Entry of BNWAS on/off
• ⁠BWL checked in deck log book and manoeuvring book.
• ⁠checked last MF/HF and VHF DSC weekly test.
• ⁠Last EPIRB self test done and where you have logged it.
• ⁠show AIS static data in AIS.
• ⁠show me VHF static data in VHF?? I told him i have to refer manual for that, he said you should have known it without seeing manual.
• ⁠checked Passage Plan.
• ⁠Handheld GMDSS walkie talkie testing records. (He just want to check that we are testing it on other channels also, except CH 16) and entry for same.
• ⁠Checked Marking on ECDIS
• ⁠presentation Library on ECDIS
• ⁠ECDIS UPS power tested by switching of the Breaker.
• ⁠BNWAS power failure alarm tested.
• ⁠checked VHF and AIS for low power mode.
• Radar performance.
• ⁠Blind & shadow sector posters for radar.
• ⁠Difference between X-band and S-Band Radar.
• ⁠would you use GMDSS walkie talkie for cargo operation.
• ⁠would you use VHF for collision avoidance. (and if no where it is written)
Place: HAWAII


BRIDGE -

1. Ecdis display settings
2. Company policy regarding Ecdis  Alarm management and same in master standing orders also.
3. CPA / TCPA / BCR in master standing orders and call master point.
4. company policy regarding BNWAS, and where you log down.
5. Difference between X & S band radar.
6. Is there any procedure stated in master standing orders regarding con with master.
7. Cyber security in detail.
8. Check the passage plan thoroughly, then check all the markings on Ecdis and verify in passage plan and verify entries in bell book / log book.
9.UKC policy as per company  procedure.
10. Check all the bridge checklist.
11. master pilot exchange and pilot Card checked thoroughly.
12. Checked all Navigation RA.
13. company policy regarding the anti grounding tool.
14. VDR self test and power failure test.
15. Difference between GPS and GNSS
16. Steering test procedure as per solas and company procedure.
17. Auto pilot settings as per company policy.
18. Checked all publications.
19. Which point you will discuss in Navigation meeting. and where you log down, Show me last Nav.meeting points.
20. Squat formula open sea and confined water.

Vessel comment: VERY VERY COOL VETTING INSPECTOR

Nil Remarks on Bridge.

PORT : MOHAMMEDIA, MOROCCO

Vessel comment: Overall approach was very practical and no nonsense was experienced during the inspection.

Deck : 
TIME TAKEN : 45 MIN
PUMPROOM : 20 MIN
CCR : 45 MIN
On deck tried out HLA ,LIFEBOAT , EMERGENCY GENERATOR 
Checked very closely heating system for cargo tanks.
Very much looking for rust spots.
Checked sample locker very thoroughly for ppe msds 
Pumproom very thoroughly checked cargo sea chest arrangement for securing .
Emergency escape arrangement.
Tried out bilge alarm.
Bwts system filters inspected.

CCR
Checked SSSCL very thoroughly.
Cargo plan 
Loadicator testing 
Cargo tank pressure alarms tried out
Questions on IG system failure 
Wind criteria 
Actions in various emergency 
Verification on LMP,MSMP.

Overall approach was very practical and no nonsense was experienced during the inspection.

Place:  Antwerp, belgium

 Master

 1. Updated hvpq and piq.

2. Defect list and company procedure for the same.

3. Updated index of certificates. 

4. Latest class survey status.

5. Last tech and marine suptt visit reports and capa.

6. Weekly, monthly lsa & ffa inspection record checked.

7. Rest hours file. Checked last drug and alcohol test record and checked timings in rest hours.

8. Hot work permit file. Vessel has no records.

9.  Ozone depleting substances record.

10.   Drill records and company procedure for the same. Risk assessment prior to the drill.

Requirement to record the safety considerations

For conducting the drill. Company generated form should cover the safety considerations.

11.  Safety inspection checklist and the areas covered.

12.   Bunker delivery notes , analysis reports and lube oil analysis procedure

 13.  Static navigational, mooring audit and cargo audit (audit report to include qualification and sea time experience of assessor.

 14.  Asked oiler in masters’ room about work planning meeting done every day. If yes, who keeps record and to bring the same.

15. Lifeboat / rescue boat lowering record.

16. Enclosed space entry procedures and drill record. Asked ab and oiler about enclosed space entry. Wanted to hear the word “permit”.

17.  Safety familiarization records and company procedure for the same. Asked ab and oiler questions from familiarization checklists.

18. Called eto in masters’ cabin and asked about fire alarm delay and 220 v / 440 v faults if any.

19. Called ab in masters’ cabin and questions on safety while working at height, in enclosed space, while mooring amongst many.

 20. Record of ballast tank inspection & cargo tank inspection checked.

21. Safe manning compared with crew list.

22. Near miss / hazrep file checked.

23. Oil record book part i, garbage record book, ballast water record checked.

 3rd officer

 1. During deck rounds, told me to start the emergency gen. Also, what all means of starting and upto what pressure to pressurise during manual hand cranking to start the generator.

2. Asked me to show gx-8000 gas meter and tell what all gases it measures, thereafter questioned the difference between lel and vol hc.

3. Asked about launching procedure and operation of davit for liferaft and rescue boat.

4. Asked difference between tankscope and explosimeter and asked if what kind of gas meter we have onboard.

5. Cause and effect of pressing ESD.

 2nd officer

 1. Asked company procedure about ecdis layer information.

2. Asked about ais not to be used for collision avoidance in company procedure.

3. Current voyage passage plan security RA.

4. Radar maintenance as per company procedures. Magnetron last changed? 

5. Speed log connected  to radar.

6. Difference between x and s band radar, when to use.

8. Master and pilot exchange with ukc sheet, min ukc required mentioned.

9. Ais testing as per company procedure , ais static data checked.

10. Master standing order with bcr and cpa. 

When master to con procedure on master standing order.

Passage plan checked (company procedures for ship staff to perform security risk assessment for the voyage.)

11. Asked about company look ahead settings and checked in ecdis

12. Steering gear test before arrival to this port, pre arrival checklist checked by inspector.

12.er watch level for each leg in passage plan.

13. Company procedure for ra to be carried out for passage plan.

14. External nav audit checked asked about the audit report to include qualification and sea time experience of assessor.

15. Bridge watch composition as per company procedure.

 Chief officer

 1. Checked ship shore safety checklist.

2. Asked for working condition of gas meters & calibration procedure

3. Bwts responsible officer for operation, procedure & maintenance schedule. 

4. Pre-cargo meeting details

5. Checked cargo plan in detail

6. Checked loadicator

7. Fgds details & calibration procedure

8. Mooring inspection records & calibration cert for press gauge of break testing kit

9. Pre arrival checks & records

10. Enclosed space entry permits & rest hours

 Deck crew

 1. Enclosed space rescue operation, permit system & company procedure

2. Rescue boat lowering procedure in detail

3. Location of esd & when to press

4. Ppe for various jobs

 Deck rounds

 General rounds and checks.

 Engine room

 1. Pipelines labelling and coding- checked pipelines.

2. Toolbox meeting and risk assessment- is there a note made anywhere that a risk assessement is discussed prior to doing jobs- 2/e work done notebook.

3. Arrival and departure checklist

4. Ums procedures and deadman’s alarm

5. Insulation mats- certification and markings on the mats. Slipping hazard.

6. Hazard markings on the stairways and steps on the platforms- zebra markings to be done.

7. Ows- operation and alarm testing procedure- sms requirement

8. Looked extensively in the bilges. We had a choked drain, which had caused oil/water emulsion to leak into the tank top. We were able to clean this up.  He looked at the work done and asked us to clean it up.

9. Blackout recovery procedure from deadship condition. Blackout test

Emergency steering procedure and last done date.

Since the annual surveyor had tested the emergency generator and did an actual blackout and deadship recovery test, sire inspector did not venture into those details ( as he had seen all the alarms and the actual process).

 

9. Fire alarm testing and procedure. What happens if the fire alarm is not acknowledged within 2 mins. And where is this given in the regulations.

Tested fire alarms. Looked at all the fire detector’s identification marks.

10. Main engine omd testing procedure and if it had been posted there in ecr.

11. Pms and overdue items.

12. Rest hours- looked at ums hours and ums alarms. Rest hours filled according to ums alarms and same logged in er log book.

12. Er log book entries for eca changeover.

14. Sulphur record book and er logbook entries matching for changeover.

15. Fuel changeover procedures and if they are posted in the ecr for reference.

16. Earth fault indicator and how to test the alarm.

17. Anti splash tapes on the fo and lo lines.

18. Nox files and entries

Orb and entries. 

19. Checked the ows 15ppm alarm testing entries and last ows operation date.

20. Manning level for engine room. Entry has to be made everyday in the er log book.

21. Garbage station in the engine room. Duties and responsibilities as per gmp to be posted in er.

22. Checked fire doors and the auto closing function. The fire doors in er was checked for proper sealing.

23. Asked about stern tube and cpp oil testing and analysis report.

 Date: 19 Jun 2025

 Port: Lagos 

 BRIDGE

 

  1. Max Anchoring depth calculation and factors to consider
  2. Max anchoring depth as per Company SMS
  3. Epirb checks (Asked in detail which all frequencies tested, which type satellites tested including AIS/ homing signals)
  4. Epirb testing frequency ( As per manufacturer required only 3 months, Company informed to amend testing frequency requirements )
  5. Which frequency for Cospas sarsat in EPIRB?
  6. When engine fails how to calculate set drift  for next 24 hrs ? (Information: Perils at sea book)
  7. Drying heights definition
  8. Name of SSO/ DPA
  9. When you will contact DPA?
  10. *Difference between LRIT / SSAS
  11. What will happen when LRIT doesnt send position report?
  12. Bridge Pyrotechnics Expiry date and checked whether they stowed in water tight casing
  13. Voyage specific security RA by 2nd off( Other than RA made by Ch off for security) 
  14. Postition Accuracy details as per catzoc( Position accuracy as per catzoc to be mentioned in passage plan notes and ukc calculation sheet)
  15. Checked passage plan thoroughly
  16. Checked no PI mark taken from drying heights
  17. How will you monitor track when you cannot use PI? ( Ans using clearing lines and bearings)
  18. Ukc policy and company procedures to follow if ukc not complied
  19. Communication equipment tests before entering HRA 
  20. Debriefing and review record after completion of  passage 
  21. Aldis lamp spare bulb/weight/testing requirements 
  22. Distraction policy poster
  23. Asked to open google for searching( To confirm Internet access not allowed on bridge) As per distraction policy
  24. Best anchoring seabed surface
  25. Catzoc details. Full explanation 
  26. Company Procedure when UKC not complied?
  27. Why AIS not to be used for collision avoidance?
  28. Why AIS status to be changed after unmooring from berth? What are the effects if we dont change?  
  29. Cross checked own ship AIS static information. 
  30. AIS testing procedures
  31. What is RAIM in dgps? 
  32. Bridge watch level poster
  33. Ukc policy poster
  34. DPA CSO poster
  35. GMDSS Radio tests and battery expiry
  36. Squat effect and importance of safe speed  while approaching berth?
  37. Master pilot information exchange form checked ( Safe speed and distance to be maintained from other moving/ moored vessels to be discussed with pilot and entry to be made)
  38. BTM meeting entries
  39.  Deck and bell book inspected.

Inspection at kashima, Japan

Nationality: Korean 

Vessel comment: Inspector was not that co operative, wanted point to point answers to his questions, didn't like beating around the bush, got upset plenty time. Didn't have any food or beverages onboard except for a cup of coffee while preparing his report in the end, didn't like disturbance of any sort while he prepared his final report.

 Bridge 

  1.  Helicopter publication (latest version is 2025) 
  2. Helicopter onboard plan, inventory of equipment
  3. Radar magnetron running hrs
  4. Defined limits of now crossing range BCR of targets in master standing orders 
  5. Defined limits of distance off navigational hazards during coastal and open sea in masters standing orders 
  6. Testing of nav lights fuse alarm 
  7. Any nav lights fused of not working 
  8. ALDIS lamp and spare bulbs
  9. AIS switched off? logged?
  10. Difference between x and s band radar
  11. Which one to use while approaching from sea to port(S band as it has better range discrimination)
  12. Which one to use while departing from ports to sea( X band as it has better bearing discrimination)
  13. Passage plan, catzoc included in UKC calculations, he wants to see if catzoc id mentioned in the UKC calculations sheet(he checked the catzoc on the enc to verify the same is reflected in the calculation sheet.)
  14. ECDIS safety settings calculations
  15. Last passage speed restrictions 
  16. Master pilot information 
  17. Entry in moment book "conn handed to pilot" 
  18. BML details as per SMS
  19.  ECDIS chart 1, date dependent object 
  20.  PL version 
  21. ENC corrected to latest week
  22. Display of shore objects on ECDIS chart 1
  23. ECIDS and bridge fam checklist 

Date : 06 July 2025 

Port : Sao Luis, Brazil 

Indian Vetting inspector but settled in brazil. 
Bridge 2hrs many questions he asked and explained also gently
Deck Rounds he said he need 1 Jun. Off/ Jun.Eng/ Deck Rating and Ch.Officer  

On brige:
1.what is backup for ecdis
2.Safet settings checked in  passage plan
3.Checked safety settings marked on ECDIS or not
4.In passage plan checked BWL & ERWL thoroughly checked. Same cross checked on Ecdis. What is LDL
5.Asked how you calculate safety setting/Ukc
6. IAMSAR manual latest edition onboard. Which volume you will find distress signals 
7. Pre-Arrival and departure check verified with checklist and bell book entries Con h/o to pilot entries, BWL who all are present and lookout & helmsman mentioned in bell book, Asked how will you include pilot in bridge team
8.You have a Manoverbaord,  what will you transmit on VHF CH16 and what type of msg you will transmit and why ?
9. Tried out dead man alarm if E/R on bridge.
  10.Checked T& p correction on Ecdis
11.Company requirement for Magnetron change.
12.In bad weather which Radar will you use & why?
13.Why X band radar not used for bad weather (diffr b/w xband and Sband)
14.Ecdis power failure checked 
15.BNWAS Monthly checks & what is level 3 Alarm
16. Asked cyber security manual and contingency plan for it. 
17. Asked why can we not reply AIS information 
18.Vdr data transfer procedure
19.Gmdss monthly weekly Record
20.Ecdis PL & week update to.
21.Steering gear test procedures.
22.From where all can find Emergency stop for  Accom. & Deck Fans( from bridge and foam room)
23.Asked who is responsible person for distress communication? And checked if it is mentioned in muster list. Asked whose is shore based company issuing certificate for gmdss 
24.Asked how you calculate look ahead. 
25.Cheked amendment plan from Anchor to berth & safety settings.
26.Checked Take me home Charts and ENC supplier
27.Asked Ecdis Display requirement as per company.
28.Asked to switch on Bnwas. I said i cant password is with only master. Asked password for master PC (I said i can common PC like bridge, CCR & ECR but master PC is password protected and only master have access to it. He was happy to hear that)
29. Asked how will you change Ecdis safety settings.( he wanted to know as per masters instruction only)
30. Checked All bridge equipments are working properly. AIS and Gyro repeater are synchronised and went on monkey island and checked magnetic compass. finally completed.

1. Deck checked more of less everything started with bridge wings, compared gyro repeaters then checked fire plan and checked if fire equipments are mentioned there.
2. ⁠Asked SCBA bottle pressure are upto mark, I said yes
3. ⁠MOB marker checked and checked weight of the buoy. Why is 4 Kg and others are not
4. ⁠Told me to start lifeboat on single battery and start cabin and canopy lights and told try out ahead and astern and wheel hard-over to hard-over 
5. ⁠Rescue boat starting procedure and strart rescue boat and checked securing straps also
6. ⁠Checked ETA manuals aft and ahead
7. ⁠Full round on deck and checked lights and emergency lights are working 
8. ⁠Went in forecastle store checked procedures for opening chain locker are stencilled
9. ⁠Was coming to accommodation asked me all fore hose box and foam hose box are mentioned in fire plan 
10. ⁠checked hospital and lights are working and hospital call button working 
11. ⁠checked foam room and and operating procedures for deck and engine room, asked bosun which foam for which area.
12. ⁠went emergency generator room, asked me to explain manual start and battery and demonstrate also. Asker 3rd eng some technical question related to it and check fuel cut off from outside generator is working.
13. ⁠Went to galley asked ch cook which all extinguisher in galley and how will activate Fixed CO2 for galley, luckily Ch. Cook ready the posted instructions and explained and finished with deck here. 

CCR:
Question 2nd officer and ch officer a lot about cargo, SSCL and Vapour line and many more
Asker Junior officer to demonstrate calibration of Multi-gas detectors 
Asked cadet to check O2 content on any tank and tell me

Capt Cabin he check all paper work throughly and checked oil record book entries of ch. eng and ch.off and compared rest hour timings. Called me in capt cabin checked all officer certification and drills timings and compared with rest hours. Many more but 
Finally at 1900 hrs did closing meeting and gave 3 observations and 19:30 he left.

Date: 11-11-2024

Place: Rotterdam, Netherlands   

ELEMENTS

 

SIRE 2.0 REF

OBSERVATIONS

Process

3.2.6     

The initial engineering audit was conducted by the vessel manager, a former chief engineer, on 29-30 May 2024. The PIQ stated 12-21 July 2024. This audit was actually conducted by a former senior deck officer.

Hardware           

5.8.1     

No proper fall prevention device (cage or equivalent stainless-steel wire with fall preventing device/belt) was fitted on the elevated ladders of the forward mast and the Xmas tree.

 

Hardware           

8.3.2     

One of both fixed oxygen detectors monitoring the air in the nitrogen generator area showed 22.2%. The PMS required a 3-monthly calibration checks. The last check was completed on 21 September 2024.Rectified during the inspection.

Human                 "Junior Engineer Officer: Not as expected.

 

 

"Junior Engineer Officer: Not as expected. The OP had not detected the high reading of one of both fixed oxygen analysers in the nitrogen generator area while the remote

oxygen reading was located near the entrance of the engine control room."

Human  "Senior Engineer Officer: Not as expected.

 

 

"Senior Engineer Officer: Not as expected.

The OP had not detected the high reading of one of both fixed oxygen analysers in the nitrogen generator area while the remote oxygen reading was located near the entrance of the engine control room."

Date: 11-11-2024

Place: Mejillones, Chile  

ELEMENTS

 

 REF

OBSERVATIONS

Human 

8.99.8   

In the midship open deck were observed 5 cargo hoses horizontally stored and they were not protected from direct sunlight (Tanker safety guide chemicals K.6.)

Process               

 

9.1.1     

The mooring winches brake testing on 07 February 2024 However there was no evidence that the pressure gauge of the hydraulic jack was calibrated before testing the brakes.

Photographs       

11.1.2   

The picture taken from port side. Also unable to see the end of the starboard side.

 

Photographs

11.1.3   

The picture shows starboard side. Unable to see the end port side of the hull.

Photographs       

 

11.1.4   

 

11.1.6   

 

 

 

11.1.19

 

 

11.1.26

 

 

11.1.42

The picture is port side.

 

Picture not taken from same angle and doesn't match the guidance photo.

 

Picture should be from Midship.

 

The picture doesn’t show the OWS.

 

The vessel was not provided with cargo pump room.

Date: 17/11/2024        

Place: Rodeo, USA                       


ELEMENTS

 

SIRE 2.0 REF

OBSERVATIONS

Hardware

 2.3.1    

There was a gap between the engine block and the deck adjacent that could provide a fall hazard

 

Process

2.8.1     

The CVIQ information was not communicated to the inspector through the tablet until 16 hours prior to the inspection which was not in line with OCIMF requirements for a SIRE 2.0 inspection.

 

Hardware           

5.10.2   

The shore gangway provided for access to the vessel was not in good condition as one of the stanchions was broken and temporarily repaired

 

Hardware           

8.3.20   

There was no separate P/V valve associated with the emergency inerting arrangement for the ballast spaces.

 

Date: 30/11/2024

Place: Singapore              

ELEMENTS

 

SIRE 2.0 REF

OBSERVATIONS

Process               

2.2.1     

The last two visits by superintendent were within 7 months, but the 2nd last and 3rd last visits as declared in the PIQ were with a gap of more than 7 months.

Hardware           

5.4.2     

A screw driver was required to open the fuel tank inspection cover for freefall lifeboat the tank fuel level. The screwdriver was missing.

Hardware

5.8.1     

Bunker line dresser coupling and it’s nuts bolts near manifolds was heavily corroded.  

Hardware

5.8.1     

Electric conduit leading to deck lamp post was corroded heavily for a length of about 2.0 M in midship area

Hardware           

5.8.2     

The exhaust pipe for hydraulic power pack with temp 58 deg C was not marked with a hot surface warning sign.

 

Process               

5.8.2     

 

Safety inspection of engine room did not identify hot surfaces liable to cause burn to human.

Hardware           

9.1.1     

The pressure gauge used for mooring winch brake testing in Apr 2024 was not calibrated before testing of winch brakes. 

 

Human

9.1.1     

OP did not follow Company procedure to calibrate the pressure gauge of winch brake testing kit before testing the winch brakes in Apr 2024.

 

Photographs       

11.1.3

The photo uploaded was not as per OCIMF guideline.

 

Photographs       

11.1.42

Vessel was fitted with Framo pumps but a photo was not uploaded by the operator.

 

Date: 02-12-2024

Place: Rotterdam, Netherlands   

ELEMENTS

 

SIRE 2.0 REF

OBSERVATIONS

Hardware           

2.4.1     

Discharging Systems: Maintenance task available — not completed. The ballast tanks external cofferdams were filled with glycol over the recommended level, which was exceeded by approximately 30%.

Hardware           

9.3.1     

Anchors And Chains: Maintenance task available — not completed. Several studs were observed damaged - they were belonging to the port side anchor cable, The observation was recorded as it was not included in the defects list presented to the inspector, which contained only closed items.

 

Several studs belonging to the port side anchor cable were found loose, thus not serving their purpose. The same anchor has been used prior entering the port.

Human

4.2.1     

The operator’s passage plan was including two sources for calculating the squat, one where the block coefficient was taken from the hydrostatic particulars and one where it was calculated. The observation was raised as the OP did not complete the form by not inserting the table values since the two block coefficient values were different, a minor value was obtained, 3 cm, this negligible.

1.            Recognition of Safety criticality of the task or associated steps

2.            Custom and practice surrounding use of procedures

 

Date : 01-12-2024

Place: Singapore

      

ELEMENTS

 

SIRE 2.0 REF

 

OBSERVATIONS

 

Hardware

2.1.1     

A short-term ballast water management system certificate was issued on 28 Nov 2024, valid until 27 Jan 2025, due to port side BWTS was inoperative due to defective flow meter, while starboard side BWTS was functional. Above finding was also recorded in the open defect list.

 

Human 

2.8.1     

1.5.6.1- Last special survey date was inaccurate.

 

 

 

10.9.1 crane last annual and 5 yearly dates were inaccurate."

 

Human 

3.2.7     

Comprehensive mooring and anchoring audit report was not available on board, however, as per the company's internal audit procedure the scope of internal audit covers the requirements of mooring and anchoring procedures.

 

Date: 27-11-2024            

Place: Tauranga, New Zealand                


ELEMENTS

 

SIRE 2.0 REF

 

OBSERVATIONS

 

Hardware           

2.4.1     

Light indication of 1S Water Ballast Tank on the control panel in Cargo Control Room was on (showing open status) while the valve was in shut position. Valve status was highlighted by ship staff by writing letter 'S' with a marker next to the valve. During the opening meeting it was reported that there were no open items in the defect reporting system.

 

Human                

 

Valve indicator issue was raised as a defect (called Findings within the computer-based reporting system) as 'Observation: OBS-V-1063' on 11 Nov 2024. However, the issue was closed out in the system on 22 Nov 2024 by OP in consultation with company's technical department, in anticipation of receipt of spares at next port, even though the issue had not yet been rectified.

 

Human

4.4.2      "Junior Deck Officer: Exceeded normal expectation

 

OP explained the procedure for use and testing of SART with reference to company procedure and on board equipment in detail.

 

Hardware           

5.8.1

 

"Water condensation droplets were visible and there was approximately 5 ml accumulation of water at the bottom of the glass cover of emergency light fitted at embarkation platform of port side lifeboat. This was rectified during the inspection.

 

Human                

 

 

During last weekly testing of emergency lights, OP did not notice the condensation and accumulation of water inside the glass cover of emergency light located at embarkation platform of port side lifeboat.

 

Hardware           

5.10.7   

 

Escape route from the accommodation to the shore means of access was not marked as required by company procedure (Oil Tanker Manual, Section 3.1.5).

 

Human                

 

OP was not aware of the company procedure which required the escape route from the accommodation to the shore means of access to be marked.

 

Photographs       

 

11.1.40

"Photo was not provided stating 'Not Fitted'. A large capacity P/V valve was fitted to the main inert gas line as pressure/vacuum-breaking (P/V) device. Photo added.

 

Date: 18-Dec-24

Port: Grangemouth, UK 

            

 

ELEMENTS

 

SIRE 2.0 REF

 

OBSERVATIONS

 

Hardware           

2.1.1

 

The continuous synopsis record form #3, record of changes, was not available on file to show the changes from CSR 1 to CSR 2. This was rectified within the inspection period.

 

Human                

2.1.1     

A previous senior deck officer had not followed the Operators procedures having not completed form #3 of the continuous synopsis record to indicate the changes made from CSR 1 to CSR 2

Process

2.8.1     

 

The HVPQ item 10.1.4 listed the motive power for all winches as being electric. The observed motive power was hydraulic.

 

PROCESS             

3.3.4     

The operator’s procedure requiring a validity of five years on engineer officers shore-based engineering management simulator course was introduced in September 2024. records indicated that one senior engineer officer had not attended a simulator course within the last five years.

 

Hardware           

5.8.1     

There were three points of direct access to the poop deck mooring area that did not have any warning signs for entering a hazardous area. This was rectified prior to completion of the inspection.

HUMAN              

9.1.1     

Previous crew members had not ensured that the manometer fitted to the hydraulic jack had been calibrated before use.    

HUMAN              

5.8.1     

The OP had not considered crew accessing the poop deck from the indicated points.

 

Hardware           

5.10.1   

The heaving line was found attached to the pilot boarding buoy.

 

HUMAN              

5.10.1   

The operators’ procedures had not been followed. The OP had not seen that the line was attached to the pilot boarding buoy prior to the inspector’s observation. The OP correctly identified the issue and rectified immediately.

 

HUMAN              

5.10.1   

The OP was not aware that the heaving line should not be attached to the pilot boarding buoy.

 

Hardware           

                                                           

9.1.1     

                                                           

There was no evidence available to show that the manometer on the hydraulic jack for winch break render tests had been calibrated prior to use.

                                                                                                        

Date: 14-Sep-24

Place: VIZAG, INDIA                       

    

ELEMENTS

 

SIRE 2.0 REF

 

OBSERVATIONS

 

HARDWARE

5.8.1

1. The port side bunker manifold flanges were heavily corroded.

2. No.4S cargo pump junction box was noted in corroded condition.

3. The electrical cables passing through branch conduits pipes of the electrical pumps of all 4 pumps were noted corroded and holed.

4. The forecastle deck, poop deck and monkey island were noted with spot rust covering about 30-40% area "            

HARDWARE        

5.8.4     

 

 

 The instinsically light at the entrance pf the compressor room was noted in corroded condition at one end.     

HARDWARE        

6.5.2     

 Solenoid valve of the incinerator was getting stuck when the sluice inside door not closed alarm was tested.              

HARDWARE        

 

9.1.1     

 

1.All the winches in the poop deck and aft spring winch were fitted with double brake bands.

2. The forward spring winch aftermost drum brake band had thinned down and cheek plates were corroded."

HARDWARE        

11.1.26

The purifier space photograph was provided instead of an oily water separator.

HARDWARE        

11.1.29

The boiler top was represented instead of control panel.                                                                

PROCESS             

2.1.1     

1. The safety construction certificate provided was not with the last endorsement of the outside of the ship's bottom which was on 12 Aug 2024 as per CSSR. The certificate available on the repository was with last bottom inspection as 25 Aug 2021.

 2. The international Air Pollution certificate (IAPPC). IAPPC record of Construction and Equipment and Conditional Asssessment Programme (CAP) certificate was not provided in the certificate repository.

3. As per the PIQ the last visit by class was 23 Sep 2023 for annual survey, whereas as per CSSR and class survey report, the class had last visited the vessel on 12 Aug 2024 for intermediate survey.                                                                                                                     4. The safety construction certificate, loadline cert, safety radio certificate, safety equipment certificate, international oil pollution cert, international ballast water management cert and certificate of fitness provided in the certificate repository were last endorsed by class on 23 Sep 2023 for annual survey and not provided with the latest endorsement for the intermediate survey on 12 Aug 2024.

 5. The safety management certificate, ship security certificate and maritime labour convention cert provided in the certificate repository did not include the latest endorsement by class dated 12 Aug 2024. 

 6. The document of compliance provided in the certificate repository did not include the latest annual endorsement for 24 Jul 2024.

PROCESS             

2.8.1     

As per the HVPQ dated Sep 2024, the following information was inaccurate:                                                                                                                                           1.  Section 1.5.11 Date of Annual survey was 12 Aug 2024, whereas this was the last date of the intermediate survey.  

2. Section 2.1.5 certificate dates a. The date of last annual for the statutory certificates was 12 Aug 2024, whereas this was the date of last intermediate survey. b. The dates of last endorsement of the statutory and applicable certificates were blank.

 3. Section 7.1.1 Cargo tank coating, the last inspection dates of cargo tanks were blank.   

4. Section 7.1.3 Ballast tank coating. No.4 DB(P&S) tanks last inspected date was 10 Sep 2023, whereas as per tank inspection reports were inspected on 06 Aug 2024.

5. Section 10.9.1 details of cranes. The last annual test of hose handling crane and provision cranes was 23 Aug 2020, whereas as per cargo gear book the last annuals of these cranes was 26 Feb 2024.

PROCESS             

3.2.2     

The details of the qualifications and pertinent seafaring experience of the assessor were not included within the navigational report.

PROCESS             

3.2.5     

The cargo audit date range and activity accessed were not declared in the PIQ.

PROCESS             

3.2.6     

The comprehensive engineering audit range and activity accessed were not declared in the PIQ.       

PROCESS             

5.8.1                    

Mooring areas were not covered in the main deck safety inspection checklist.              

PROCESS             

5.8.5     

There was no checklist provided to facilitate the safety inspections of the forecastle.

PROCESS

 

 

 

8.6.4     

Emergency procedures single tank gas-freeing was not included in the cargo operational manual.

HUMAN              

2.4.1     

The company's procedure required defects to be input in the PMS, 7 defects were input in the other in-house software JIbe and were not recorded in the PMS.

HUMAN              

 

4.3.2     

The composition of the engine room team was not recorded in the engine log book. Only E2 watch level recorded without the no of persons

HUMAN              

4.3.3     

The times of the transfer of the conn between the master and between the Pilot and master was not recorded in the bell book or deck log book.

HUMAN

5.4.1     

The OP was not aware of the onload release mechanism of the lifeboat.  

DATE: 22-Dec-24

PORT: Finland - Porvoo

ELEMENTS

 

 REF

 

OBSERVATIONS

 

PROCESS

3.2.1     

The static navigational assessment report was not substantially in alignment with the guidance document "A Guide to Best Practice for Navigational Assessments and Audits" and the best practice guidance under TMSA KPI 5.2.2.

PROCESS             

3.2.5     

The cargo audit report stated in the PIQ was part of the ISM audit and not a comprehensive cargo audit in compliance with TMSA 6.4.2

 

PROCESS             

8.6.1     

The operator did not have a policy or PMS job for the required IGC code 13.3.5. (at the first occasion of full loading after delivery and after each dry docking, testing of high-level alarms is to be conducted by raising the cargo liquid level in the cargo tank to the alarm point).

 

HUMAN              

8.6.1     

The required IGC test 13.3.5, testing of high-level alarms to be done at first full loading after delivery. Vessel delivered March 2023 and test carried out December 2024.

 

PROCESS             

 

8.6.3     

There were no records available of inspections, tests and maintenance carried out on the cargo tank relief valves including: Six-monthly visual inspections. Annual verification of free operation using a field test kit, according to the vessel operational manual (Maker’s manual).

 

Human: The following tests required by the maker could not be documented: Six-monthly visual inspections. Annual verification of free operation using a field test kit, where applicable according to the vessel operational manual and/or instructions.

 

Human

8.6.3

The following tests required by the maker could not be documented: Six-monthly visual inspections. Annual verification of free operation using a field test kit, where applicable according to the vessel operational manual and/or instructions

 

HUMAN

9.1.1     

The hydraulic jack pressure gauge had not been calibrated before use 05 March 2024.

 

Date: 18-Dec-24

Port: Grangemouth, UK 

        

 

ELEMENTS

 

SIRE 2.0 REF

 

OBSERVATIONS

 

Hardware           

2.1.1

 

The continuous synopsis record form #3, record of changes, was not available on file to show the changes from CSR 1 to CSR 2. This was rectified within the inspection period.

 

Human                

2.1.1     

A previous senior deck officer had not followed the Operators procedures having not completed form #3 of the continuous synopsis record to indicate the changes made from CSR 1 to CSR 2

Process

2.8.1     

 

The HVPQ item 10.1.4 listed the motive power for all winches as being electric. The observed motive power was hydraulic.

 

PROCESS             

3.3.4     

The operator’s procedure requiring a validity of five years on engineer officers shore-based engineering management simulator course was introduced in September 2024. records indicated that one senior engineer officer had not attended a simulator course within the last five years.

 

Hardware           

5.8.1     

There were three points of direct access to the poop deck mooring area that did not have any warning signs for entering a hazardous area. This was rectified prior to completion of the inspection.

HUMAN              

9.1.1     

Previous crew members had not ensured that the manometer fitted to the hydraulic jack had been calibrated before use.    

HUMAN              

5.8.1     

The OP had not considered crew accessing the poop deck from the indicated points.

 

Hardware           

5.10.1   

The heaving line was found attached to the pilot boarding buoy.

 

HUMAN              

5.10.1   

The operators’ procedures had not been followed. The OP had not seen that the line was attached to the pilot boarding buoy prior to the inspector’s observation. The OP correctly identified the issue and rectified immediately.

 

HUMAN              

5.10.1   

The OP was not aware that the heaving line should not be attached to the pilot boarding buoy.

 

Hardware           

                                                           

9.1.1     

                                                           

There was no evidence available to show that the manometer on the hydraulic jack for winch break render tests had been calibrated prior to use.

                                                                                                        

Date: 23-Dec-24              

Port : Unites States of America - Freeport                             

         

 

ELEMENTS

 

SIRE 2.0 REF

 

OBSERVATIONS

 

HARDWARE        

2.4.1     

 

Fixed temperature readout for no.3 cargo tank middle was showing about (-) 2 degrees more than that of other tanks. The difference persisted on previous cargo operation.

 

HUMAN              

2.4.1     

OP did not include the erratic readout temperature sensor in defect list for middle level of cargo tank no 3P.

 

PROCESS

 

12.2.1   

Question no. 4.1.1, 10.1.3.2, 10.1.6, 10.2.1, 10.8, 10.10.6, 10.10.7 & 11.3 were incomplete or blank.

 

HUMAN              

3.5.1     

Safety and security familiarization checklists for the operator's superintendent who stayed onboard from 25 to 27 Nov 2024 were left blank for following sections: 1. Time of boarding. 2. Time familiarization completed. 3. Important information containing 11 items being required to be ticked.

 

PROCESS             

4.2.3     

Master's standing order did not include the minimum BCR permitted during normal navigational watches. The minimum required BCR of 2 miles was added to the standing order during the inspection.

 

HUMAN              

5.1.16   

 

The drill scenarios were unrealistic or inadequate to test the shipboard emergency plan. Last two 6 monthly drill records dated 25 Apr and 30 Oct 2024 were the same with wording, scenario, and location of the engine room.

 

HUMAN              

 

5.5.1     

OP in charge of the paint store was not aware of the location of exhaust fan switch for the space. A notice 'Ventilate before entry' was prominently marked at the entrance door.

 

HARDWARE        

 

5.6.1     

 

A portable multi gas detector measuring for O2 and HC in inerted condition was found in erratic readout when sampling oxygen content in cargo hold no.3 as indicated over 8.5%, while oxygen content sampled by two other detectors showed below 5%. The detector was made operational after recalibration.

 

HARDWARE        

9.1.1     

The hydraulic jack pressure gauge had not been calibrated before use where brake testing equipment was carried. A requisition for calibration was raised.

 

 

 Date: 08-Jan-25

PORT: Singapore                             


ELEMENTS

 

SIRE 2.0 REF

 

OBSERVATIONS

 

Process               

2.2.1     

The report by the marine superintendent was not available onboard for the declared qualifying vessel inspection conducted from 26 December 2024 to 27 December 2024.

 

Process               

 

3.2.7     

The report for the comprehensive mooring and anchoring audit declared through the pre-inspection questionnaire was not available onboard.

 

Process               

6.5.2     

A list of items prohibited from being incinerated was not posted in the incinerator space. The list of prohibited items was posted and observation was rectified during the inspection.

 

Human

 

6.5.2     

 

The interviewed engineer officer was unfamiliar with the posting of information regarding prohibited items from being incinerated.

 

DATE: 22-Dec-24

PORT: Finland - Porvoo

ELEMENTS

 

SIRE 2.0 REF

 

OBSERVATIONS

 

PROCESS

3.2.1     

The static navigational assessment report was not substantially in alignment with the guidance document "A Guide to Best Practice for Navigational Assessments and Audits" and the best practice guidance under TMSA KPI 5.2.2.

PROCESS             

3.2.5     

The cargo audit report stated in the PIQ was part of the ISM audit and not a comprehensive cargo audit in compliance with TMSA 6.4.2

 

PROCESS             

8.6.1     

The operator did not have a policy or PMS job for the required IGC code 13.3.5. (at the first occasion of full loading after delivery and after each dry docking, testing of high-level alarms is to be conducted by raising the cargo liquid level in the cargo tank to the alarm point).

 

HUMAN              

8.6.1     

The required IGC test 13.3.5, testing of high-level alarms to be done at first full loading after delivery. Vessel delivered March 2023 and test carried out December 2024.

 

PROCESS             

 

8.6.3     

There were no records available of inspections, tests and maintenance carried out on the cargo tank relief valves including: Six-monthly visual inspections. Annual verification of free operation using a field test kit, according to the vessel operational manual (Maker’s manual).

 

Human: The following tests required by the maker could not be documented: Six-monthly visual inspections. Annual verification of free operation using a field test kit, where applicable according to the vessel operational manual and/or instructions.

 

Human

8.6.3

The following tests required by the maker could not be documented: Six-monthly visual inspections. Annual verification of free operation using a field test kit, where applicable according to the vessel operational manual and/or instructions

 

HUMAN

9.1.1     

The hydraulic jack pressure gauge had not been calibrated before use 05 March 2024.

 

Date: 03.Sep.2024

Place: Nipah Anchorage, Indonesia 

Total time: Around 10 hours

Inspector boarded in the morning and started his tablet near gangway only. 

After being briefed by gangway crew, asked him about various alarms on ship like general emergency, fire alarm,  cargo onboard. 

Then to the Master's cabin & started opening meeting 

  1. Ship certificates...
  2. In between asked abt the cyber security manual & procedures..
  3. Ship's defect list if any...cross questioning in that...

Bridge

  1. Company procedures to operate RADAR/ARPA
  2. Echo sounder alarm settings 
  3. VDR data recovery procedure 
  4. Thoroughly checked passage plan
  5. GMDSS logbook 
  6. UKC policy & some other normal questions 

 CCR

  1. asked about last decanting ODME printout
  2. Desloping receipts
  3. Gas meter calibration... checked calibration of one meter 
  4. Checked all gas measuring equipments including drager pumps
  5. FGDS...if any alarms 
  6. Checked cargo plan & SSSCL thoroughly 
  7. Manual reference to pressure settings 
  8. Simulation of pressure alarms 
  9. Manual reference to use of respiratory equipments in cargo operations 
  10. Manual reference to trainees not allowed to use moorings without supervision 
  11. Manual reference for daily work planner 
  12. Last COW records & checked port log too for O2 checks entry...
  13. Basic cross questioning to duty officer 
  14. IG not working procedure & manual reference 
  15. Pump room checks PMS
  16. 20 mins of questioning in CCR of Chief officer

Galley.

  1. Asked chief cook abt fire fighting equipment's in galley 
  2. Deep fat fryer maintenance & who is doing it

Deck & pump room 

  1. General rounds & sone basic cross questioning like PV breaker, mast riser, IG non return valve maintenance schedule in PMS

LSA

  1. Checked lifeboat engines 
  2. Rescue boat engines 
  3. Paint room sprinkler system tried

Ballast tank

  1. Checked condition of one ballast tank 

Deck machinery

  1. Checked operation of deck machinery like winches

ECR

  1. Checked logbook thoroughly 
  2. Bunker checklist 
  3. Various equipments & PMS
  4. Asked some basic questions to oiler in smoke room like boat station... emergency alarms etc.

Questions asked by SIRE 2.0  Inspector

  1. Emergency DG should supply power for how many hours. Who/what decides its 18 and not 19 or 17.
  2. Steering gear reserve tank gauge. How much is it supposed to be.
  3. In case of flooding in ER what is the first action
  4. Running AE stops/trips. What happens next. ( what is time taken by emergency DG to come on load vs Stby DG to come on load)
  5. Why is rudder movement checked from 35-0-30 and not 35-0-35
  6. Steering gear failure from bridge. What action will be taken 
  7. Bridge telegraph not operational. What action to be taken.
  8. 20 mins of questioning in ECR of 2AE and 1AE